Bulk Upload Multiple Projects to Hub Planner

Estimated reading time: 4 min

Where do I Start?

There are two places where you can easily bulk upload multiple projects from. Settings or straight from the Scheduler.

Add Multiple Projects from Scheduler

Add multiple projects direct from the scheduler. Using the sidebar ‘Add New’, clicking the 3 vertical dots of new project allows you to bulk add multiple projects. Bulk_Add_projects

  1. Scheduler
  2. Sidebar
  3. Click ‘Add New’ for the drop down list
  4. Click 3 vertical dots of ‘New Project’
  5. Select ‘Bulk Add Projects’
  6. Opens the Bulk Add Projects modal.

Bulk_Upload_projects

Bulk upload from Settings:

Navigate to ‘Settings’. Scroll along the sidebar to ‘Manage’. Select ‘Manage Projects’ from the sidebar drop down list. Here you have sight of all you current projects within Hub Planner. There are also two versions of bulk uploading. Both achieve more or less the same result.  Just choose which one is good for you.

  1. Settings
  2. Manage
  3. Manage Projects
  4. Add Projects
  5. Add Multiple Projects

Manage_Projects_Bulk_Upload_projects_HubPlanner

The Bulk Upload Modal

Paste project data

The first tab ‘Paste’ allows you to simply and easily add the field data in the text box separating data with a comma. Add multiple projects by entering to the next line. Once ready, click ‘Continue’. Then you will assign the values. For example, in the below image I’ve added two projects under the headers of: Project name, project code, project default rate, project budget cash amount, project currency, project start date and project end date.

Bulk_Upload_projects

Upload from file 

An alternative option is to upload the data from a .csv or excel file.

Bulk_Upload_projects

Once you pasted or uploaded your file. You will then assign the headers to the values.

Assigning Values

Using the example above of pasting the data into the Paste tab: It will also look the same if I uploaded from a .csv or .xls file.

Bulk_Upload_projects

Now I assign the headers to the columns:

Bulk_Upload_projects

Once ready, select ‘import’. You will see a ‘successful’ pop up and documenting the quantity of newly created or updated projects.

What the project will look like based on the above example: You can see that it has assigned the values to the correct fields.

Bulk_Upload_projects

How to Download the .csv template?

You can download the .csv template to bulk upload projects via here

What are the header options for Bulk Uploading Projects?

The following options are valid for bulk uploading projects.

  • Project Name Bulk_Add_Projects_Upload
  • Project Code
  • Group
  • Note
  • Budget (hours)
  • Budget (cash)
  • Project Budget Currency
  • Start Date (YYYY-MM-DD)
  • End Date (YYYY-MM-DD)
  • Status

Name

name – (required)

  • Type Name of Project (Unique)

Project Code

projectCode

  • Code to identify project (Can be used to overwrite the existing project)

Assign Project to New or Existing Project Group

group

  • Text – Enter the name of an existing or new group for this project to belong to.

Project Notes

note

  • Plain Text
  • Empty (Default – No note)

Overall Project Budget

budget

  • hours
  • cash
  • Empty (Default – No budget)

Default Project Hours Budget

projectBudgetHours

  • Empty (Default – 0 hours)
  • Integer e.g. 50
  • Only valid if hours chosen in budget

Default Project Cash Budget

projectBudgetCash

  • Empty (Default – 0)
  • Integer e.g. 7000
  • Only valid if cash chosen in budget

Assign Default Project Rate

projectBudgetBillingRateDefault

  • Empty (Default TRUE)
  • TRUE (Use default billing rate defined in Settings)
  • FALSE (USE CUSTOM BILLING RATE)

Optional Project Rate

projectBudgetBillingRate

  • Empty (Default 0)
  • Integer e.g. 250

Project Status

status

  • active (Default if left blank)
  • archived
  • pending
  • planned
  • floating

Project Start Date

start

  • Start Date (Format YYYY-MM-DD)

Project End Date

end

  • End Date (Format YYYY-MM-DD)

Project 3rd Party Links

link 1- 5

  • Links for project
  • Empty (default  No links)

Company Working Days

sunday – monday

  • Empty (Default to company working days defined in Settings)
  • TRUE – Sets the day to working
  • FALSE – Sets the day to not working

How do I Upload my template?

  1. Settings
  2. Manage
  3. Manage Projects
  4. Add New Projects | Bookings
  5. Add Multiple Projects
  6. A pop up will appear
  7. Select File
  8. Upload
  9. Your Projects Will Now Appear within the Scheduler Sidebar

I need more help on hot to Bulk Upload Projects?

Sure, send us a message via hello@hubplanner.com

Bulk Update Projects

Perhaps you want to complete a bulk status update. Or assign project codes to all projects in bulk etc.

Following the same steps as above, you can identify your project by the project code. Ensure that all uppercase/lowercase are adhered to. For example, I want to update project BMW from Active to Archived.

Bulk_Update_Projects_Hub_Planner

Step 1 – Add Project Details to the Uploader

Using a comma to separate the data, type or paste into the text box. For this scenario, all I need is the Project Name, the Project Code and the Project Status I want to update the project to.

  • Project Name = BMW
  • Project Code = CodeBMW1
  • Status = Archived

Bulk_Update_Projects_Hub_Planner

Step 2 – Assign the Values

Apply the headers from the dropdown list of each column. And press Import

  • Project Name = BMW
  • Project Code = CodeBMW1
  • Status = Archived

Bulk_Update_Projects_Hub_Planner

Once imported, the system will detail the results of the import.

Bulk_Update_Projects_Hub_Planner

You can now see that the status of the BMW project has been successfully updated from Active to Archived.

Bulk_Update_Projects_Hub_Planner